GeoEngineers, Inc
Expertise About Us News Case Studies Sustainability
Careers Contact Us Feedback Client Portal Reset Password
Skip Navigation Links.
Skip Navigation Links.
Expand locationlocation
Expand marketmarket
Expand serviceservice
Line
North Napa Bypass and Siphon Project
Market Icon

Project: North Napa Bypass and Siphon Project

Where: Napa, California

Overview

Napa Sanitation and Flood Control District undertook the North Napa Bypass and Siphon Project to relocate existing 36-inch and 45-inch diameter sewers out of the U.S. Army Corps of Engineers’ Napa River Flood Control Protection Project area.

The main challenge of the project was the design and construction of a siphon undercrossing of the Napa River. The new bypass sewer and siphon allowed the District to eliminate two existing pump stations.

Approach

A series of geotechnical test borings were completed along the pipeline alignment. The geotechnical investigation also included research into geologic setting, development history along the alignment, coordination with U.S. Army Corps of Engineers work, and construction precedent for past Napa River undercrossings.

Both horizontal directional drilling and microtunneling were considered for construction of the siphon beneath the Napa River. Due to limited surface area on either side of the crossing, microtunneling was selected as the crossing method.

The presence of cobbles and boulders was documented in both the project field investigation and the construction records for a nearby tunnel undercrossing of the Napa River. As a result, it was recommended to change the design of the siphon from twin 30- inch diameter pipelines within separately installed 36-inch diameter steel casings to installation of the twin 30-inch pipelines within a single 72-inch diameter steel casing. The switch to a larger casing (and thereby larger tunneling machine) provided increased ability to ingest cobbles and boulders.

Other project challenges included the design and construction of 55-foot deep ‘watertight’ shafts for tunneling, and a section of “inclined” tunneling at over 15% upslope which required significant modifications to standard tunneling equipment and procedures.

Results

  • The siphon undercrossing of the Napa River was successfully completed despite encountering cobbles and boulders.
  • The new bypass sewer and siphon allowed the District to eliminate two existing pump stations.

Facts

  • Overall Project: 3,365 feet of 48-inch diameter gravity-flow sanitary sewer pipeline
  • Microtunnel Tunnel Drive Lengths (72-inch diameter steel casing): 300 feet and 250 feet
  • Project details were summarized in a technical paper presented at the 2007 North American No-Dig Conference in San Diego, California. The paper was given the Outstanding Paper Award for New Construction.
  • Lead GeoEngineers office: Walnut Creek