GeoEngineers provided expert horizontal directional drilling (HDD) design and construction consulting services for a shore approach installation of a crude oil export pipeline off the southeastern coast of Trinidad. The New Oil Export Line (NOEL) project called for a 30-inch-diameter pipeline coated with 1.85 inches of concrete installed under the sea floor. The combination of a large pipe diameter, concrete coating and long distance of 5,780 feet made the NOEL HDD shore approach installation a world record.
The NOEL project featured a long HDD crossing with the added challenge of a heavier-than-normal, rigid, concrete-coated pipe. The GeoEngineers design team analyzed where drilling would start and end, how much force HDD construction equipment could bear and how well the pipe would curve when pulled back through the hole under the sea floor.
GeoEngineers documented HDD construction contractor actions during drilling of the initial 12-inch hole underground, enlarging of the hole and pulling the pipe through the hole from the offshore exit location to the onshore drilling entry site.
The HDD installation required significant project coordination within the BP Trinidad and Tobago (BPTT) facility and between onshore, offshore and HDD construction contractors.
ACEC-Missouri Engineering Excellence Awards, Grand Award, Energy Category, 2009
Winston Mohammed,
Project General Manager
NOEL